Rehabilitating the Lekki-Ajah road: Lagos will open the Coastal Road and other routes

Table of Contents

The Lagos State Government has outlined its plans to avoid traffic jams and lessen the effects of the ongoing

Lekki-Ajah road renovation on drivers.


It said that alternate routes, such as the Coastal Road and nearby service lanes, are being improved and opened to lessen disruption and offer more seamless diversions as needed.

In order to ensure that the majority of construction activity occurs during times when traffic volume is much lower, the government said that it has implemented a night-shift approach for key portions of the repair work.

The Lagos State Government acknowledged the worries raised by locals and commuters about the restoration of the Lekki–Ajah corridor in a message posted on its official X (previously Twitter) account.

The Lagos State Government stated that it understands these worries, particularly as the busy holiday season draws near, and wants to give all drivers clarification.

Phased rehabilitation

According to the state government, the rehabilitation efforts will be carried out in well-thought-out stages to avoid interfering with regular activities. It stated that only certain portions of the corridor will be repaired at any one time, and that these portions were specifically picked to have as little of an impact as possible on the main carriageway.

It clarified that extensive strategies for managing traffic during peak hours had also been implemented by the government.

It further stated that Lagos State Traffic Management Authority (LASTMA) staff will be stationed in sufficient numbers throughout the entire stretch to guarantee uninterrupted traffic flow, avoid bottlenecks, and react quickly to any traffic pressure that may develop during the restoration phase.

The goal of the rehabilitation project is to make the Lekki–Ajah corridor better, not to make the locals more uncomfortable. As we strive to provide long-term solutions that will make commuting safer, quicker, and more convenient for everyone, the government asks for cooperation and patience.

The Lagos State Government stated that it is still dedicated to delivering top-notch infrastructure and will keep interacting with the public as the project develops.

Things you should be aware of

An significant road restoration project along the Lekki-Ajah corridor was announced by the Lagos State Government on Wednesday, November 12, 2025. The project would run for eight months, from November 15, 2025, to July 15, 2026.


In one of the busiest transit routes in the city, the effort seeks to enhance road infrastructure and reduce ongoing traffic congestion.

In order to minimize commuter interruption, the administration stressed that the project will be implemented in two strategic phases.

Phase 1: Work will be completed in seven sections from the Lekki first toll gate to the Lekki second toll gate.

Phase 2 will be split into four portions and will span the area from the Lekki second toll gate to the Ajah under-bridge.